5 Changeover Mistakes That Are Killing Your Can Line Speed
I've spent years on beverage canning floors, and the same changeover mistakes show up at almost every facility. Here are the top 5 I see — and what to do instead.
1. No standardized changeover checklist
Every operator does it differently. That variance alone can add 15-30 minutes per changeover. Document the fastest operator's method and make it the standard.
2. Waiting for maintenance to show up
If your operators can't handle basic size-change adjustments themselves, you're losing time every single run. Cross-train them on the mechanical basics.
3. Not pre-staging materials
Lids, labels, and cans for the next run should be staged BEFORE the current run ends. Sounds obvious, but I still see crews scrambling after the last can comes off.
4. Ignoring the filler-to-seamer handoff
This is where most hidden downtime lives. If your seamer isn't dialed in before the filler starts pushing cans, you're going to jam and lose 10+ minutes recovering.
5. Skipping the post-changeover audit
Run 50 cans and check seam quality, fill levels, and label placement BEFORE ramping to full speed. Catching a problem at 200 CPM is a lot cheaper than catching it at 1,200.
I teach maintenance techs and line engineers how to eliminate these kinds of issues systematically inside Line Speed Academy.