5 things property developers get wrong about construction timelines
After years of building for developers and investors across SA, I keep seeing the same mistakes that blow out timelines and budgets. Here's what I've learned:
1. Starting without proper soil testing
You'd be shocked how many projects get delayed 4-6 weeks because of unexpected ground conditions. A R5k test upfront saves you R500k in surprises.
2. Not locking in materials early
Steel and cement prices move. If you're not securing supply 30-60 days before groundbreak, you're gambling with your margins.
3. Underestimating municipal approvals
Building plan approvals in most metros are taking 8-12 weeks right now. Factor this into your project timeline from day one.
4. Skipping the phased handover
Instead of one big handover at the end, break it into phases. It lets you start earning rental income or selling units while the final phase wraps up.
5. Choosing the cheapest contractor
The cheapest quote usually means the most expensive project. Rework, delays, and substandard finishes cost more than paying for quality upfront.
At Ibuild, we help developers avoid exactly these pitfalls. If you've got a project coming up, request a free consultation — we'll give you a realistic timeline and budget before you commit.